Bartlett

This project encompassed the design and build of M&E services to an existing office building occupied by Bartlett. The old part of the building was refurbished in the 70’s and a new extension built in the mid 90’s.

Although primarily an office environment installation, the project included training rooms, reception, business lounge, gymnasium and server room.

Project Overview

  • Project Title: Office Refurbishment
  • Client: Bartlett Group
  • Main Contractor: Brown and Bancroft
  • Client Architect / M&E Services Designer: Space Invaders
  • Design and Build Mechanical Contractor Impact — Electrical Contractor Richardson’s
  • Project Duration: 48 weeks M&E Installation
  • Project Value: £1.4m
  • M&E Package Value: M £440k , E £250k

Aura’s Role

Aura Technical Services was employed by Brown and Bancroft to manage their Mechanical and Electrical contractor, Impact Mechanical and Richardson’s Electrical.

Detailed responsibilities included:

  • Manage and coordinate the pre-construction phase
  • Manage and coordinate the construction phase
  • Manage and coordinate the commissioning phase