VW Stoke Refurbishment

Project Overview

  • Client: Clare James Automotive
  • Main Contractor: Bedaro
  • Client M&E Services Designer: KGA Partnership, Liverpool
  • Design and Build M&E Contractor – Aura Technical Services Ltd
  • Project Duration: 12 weeks
  • Project Value: £1.5m
  • M&E Package Value: £180k

Aura’s Role

Aura Technical Services was employed by Bedaro to undertake the complete design, installation and commissioning of the VW Stoke refurbishment project. The project was completed in a live environment whist the dealership continued to operate.

The project involved:

  • New EXOR lighting controls system
  • New music system
  • New IT and data infrastructure
  • New small power installation
  • New feature lighting installation
  • New VRF heating an cooling installation
  • Modifications to the existing domestic water installation
  • Modifications to the existing ventilation system